90 persons can complete a job in 32 days. 12 days after they started working, 60 more persons joined them. How many days will they now take to complete the remaining work?

(A) 10 Days
(B) 12 Days
(C) 14 Days
(D) 16 Days

»Important Links:

English McqsGeneral Knowledge McqsPak Studies Mcqs
Current Affairs McqsCurrent Affairs Mcqs PDFCurrent Affairs of Pakistan
Books PDFNotes PDFIslamic Studies Mcqs

Leave a Reply

Your email address will not be published. Required fields are marked *

error: Content is protected !!