Aslam can do a piece of job in 60 days. He works at it for 4 days and then Ali alone finishes the remaining work in28 days. In how much time will Aslam and Ali working together, finish the work?

(A) 20 Days
(B) 25 Days
(C) 30 Days
(D) 35 Days